Rochester Hub: Initial Estimate of Capital Investment to Complete
Construction
Estimated Capital Investment
$1,200
Spend through September 30, 2023
$1,000
Balance spend
$800
1
2
$600
$400
$560M
1 + 2
$700M
$200
$140M
$394
$301
г
$92
$0
Rochester Hub
Capex
Process &
Warehouse
Buildings
Total
Rochester Hub +
Buildings
Note: Capex figures may not add to total due to rounding; (1) As of September 30, 2023
~$1,000M
-$850
Initial Estimated
Range, depending on
the option selected
Commentary
Rochester Hub capex spend to date was
~$301M(1) as compared to previously
disclosed $560M construction budget
➤ Incremental spend for process buildings
and warehouse of -$92M (1) to date as
compared to estimated total cost of
~$140M
➤ Depending on the option selected, initial
estimated capital cost to be in the range of
approximately $850M to approximately
$1B, including buildings
➤ Detailed analysis work undergoing
including updated timing, and revised
contracting strategy
Ⓡ