Investor Presentaiton
Rosh Pinah "RP2.0" Expansion
Pre-Feasibility study highlights (August 2020)
1.3Mtpa Mill
Modified plant to include
SAG mill, crushing and
ore blending system
Paste Fill Plant
Will reduce surface tailings as
redirected underground as paste fill
Paste Fill
Will increase ore recovery
and reduce dilution
WF3
Portal
Dedicated portal
for WF3 deposit
SOF
New Trucking Decline &
Mobile Equipment Fleet
Upgade from 30t to 60t trucks
Reduction in hauling distance and traffic
Improved ventilation
ROSH PINAH 2.0
Looking North East
EOF
TREVALI
Single stage SAG mill
crushing and ore
blending system with a
nominal throughput
increase from 0.7 to 1.3
Mtpa.
Paste fill plant and
reticulation system will
reduce surface tailings
and mining dilution
while increasing ore
recovery.
Dedicated portal and
decline with associated
infrastructure for the
WF3 deposit.
Project Capital Cost of
$93M and Construction of
the expansion project
assumed to commence in
Q1 2022 and commercial
production to be
achieved by start of Q1
2023.
Underground mobile
equipment moving
from 30 to 60 tonne
haul trucks.
Note: refer to the Company's August 25, 2020 news release for full details.