GETTING THE JOB DONE BUDGET 2019 Manitoba Hydro Capital Initiatives āœ“ Manitoba Hydro is currently investing in a major generation project and has put into service a major transmission project. Keeyask Hydro Generating Station Project Design Capacity: 695 MW Anticipated First Unit in Service Date: 2020-21 Anticipated Cost: $8.7B Bipole III Transmission Line Project Design Capacity: 1,364 km In Service Date: July 4, 2018 Anticipated Cost: Approx. $4.8B Manitoba