Doubling the Townsend Gas Processing Complex
Received regulatory approval for the doubling
of the Townsend Facility to 396 Mmcf/d and to
retrofit the existing 198 Mmcf/d shallow-cut
Townsend Facility to a deep-cut facility at a
future date
Townsend phase 2
■
Townsend Phase 2 will be constructed in two
separate gas processing trains
The first train (2A) is a 99 Mmcf/d shallow-cut
natural gas processing facility located on the
existing Townsend site
-
On-stream October 1, 2017
Fully contracted under a 20-year take or pay with
Painted Pony
The $125 million project was completed slightly
ahead of schedule and approximately $5 million
under budget
The second train (2B) is under development with
a target on-stream date of 2019/2020