Investor Presentaiton
eneva
Portfolio......
At the end of 2021,
our businesses
focused on:
Power generation: With an electric generation
park of 3.1 GW of installed capacity (71%
operational), we generate safe and competitive
energy for the Brazilian electrical system,
representing 9% of the country's gas-fired
thermal capacity. In the segment, our portfolio
consisted of nine thermoelectric generation
plants (two under construction and one under
commission), a solar plant and a wind farm under
development, in addition to assets focused on
Distributed Generation.
> Maranhão - we own the Parnaíba Complex,
formed by natural gas plants Parnaíba I,
Parnaíba II, Parnaíba III and Parnaíba IV with 1.4
GW, and two projects in development, Parnaiba
V and Parnaiba VI, with 477 MW. In addition, we
operate Itaqui plant, coal-fired, with 360 MW.
1) 3.7 GW from 2022, considering Futura I solar plant, under
construction in the period.
> Ceará - we operate the Pecém II plant with 365
MW of coal-fired generation. We are also
responsible for Tauá Plant (1 MW), the first solar
plant to generate electricity on a commercial
scale in Brazil, as well as its 64 MW expansion,
which already has approved environmental
licenses.
> Roraima - Natural Gas plant Jaguatirica II, with
142 MW.
> Rio Grande do Norte - we developed the
Santo Expedito Wind Farm, with all licenses
approved for its construction, with 330 MW.
In addition to these assets, we will start, in 2022,
in Amazonas, the construction of TPP Azulão
(295 MW), expanding the R2W model to the
state, where we already operate the Azulão gas
treatment plant (GTP). The new plant, which will
require investments of R$ 1.3 billion, was made
possible in 2021, in the energy capacity auction,
held by the Brazilian Ministry of Mines and Energy
(MME), on December 21. At the end of the year,
we also owned the Santo Expedito Wind Power
Project, in final licensing phase. The project,
of wind generation, located in Rio Grande do
Norte, will have 333 MW of installed power and a
capacity factor (P50) of 57.5%.
sustainability report 2021
Futura | construction, Juazeiro, BA
<16>
about us
=View entire presentation