FY17 PRODUCTION PERFORMANCE
Production by upstream operation¹
WORSLEY ALUMINA
BRAZIL ALUMINA
SOUTH AFRICA ENERGY COAL - DOMESTIC COAL
SOUTH AFRICA ENERGY COAL - EXPORT COAL
ILLAWARRA METALLURGICAL COAL² - METALLURGICAL COAL
ILLAWARRA METALLURGICAL COAL² - ENERGY COAL
AUSTRALIA MANGANESE- ORE
CERRO MATOSO
CANNINGTON - SILVER
CANNINGTON - LEAD
CANNINGTON - ZINC
9M YTD17 Q4 FY17 guidance
0%
25%
50%
75%
100%
South32 share. Production guidance not provided for our Aluminium Smelters and South Africa Manganese ore, which remains subject to market demand.
Illawarra Metallurgical Coal FY17 production guidance to be updated following the 10 May 2017 ASX, JSE & LSE announcement. Based on prior guidance of 7.9Mtpa.
Annualised rate of 3.8Mwmt achieved during the March 2017 Quarter
Notes:
1.
2.
3.
16 MAY 2017
BANK OF AMERICA MERRILL LYNCH - GLOBAL METALS, MINING & STEEL CONFERENCE
Investing in our operations
EIII
IIIE
SOUTH 32
Nearing completion of the first panel at Illawarra
Metallurgical Coal's Appin Area 9
Delivered first ore from the higher grade
La Esmeralda deposit at Cerro Matoso
Completed Premium Concentrate Ore project
ramp-up at Australia Manganese
Commissioned Wessels Central Block and
increased ore production³ at South Africa
Manganese in response to market conditions
Developing new mining areas at
South Africa Energy Coal
Maintained benchmark levels of operating
efficiency at our Aluminium smelters