Enbridge Operations and Financial Update slide image

Enbridge Operations and Financial Update

Renewables: Offshore Project Execution ~4.5GW in Construction & Development 1,2 UK Ireland Albatros | 2019 Dunkirk | 580 MW3 Rampion | 2018 Hohe See | 2019 Calvados | 2024 Renewable power: (facility | est. ISD) In operation Under construction Awarded Germany Fécamp | 2023 Saint Nazaire | Late 2022 France Provence Grand Large | 24 MW3 EENBRIDGE Saint Nazaire 480 MW (122 MW net) 35 of 80 foundations installed • On track for late 2022 ISD Fécamp 497 MW (89MW net) ⚫ Foundation fabrication underway On track for 2023 ISD Calvados 448 MW (97 MW net) Substation platform & cable manufacturing On track for 2024 ISD Offshore renewable projects progressing on budget and on schedule (1)~1GW of net ownership (2) Development projects includes additional projects not identified on the map (3) Project has been awarded, but not yet reached FID, gross operating capacity (combined net capacity 0.2 GW) 17
View entire presentation