Maules Creek Impacted by H1 flooding / weather, labour shortages and AHS constraints 19 FY23 ROM production of 9.6Mt, 15% below FY22 due to: - localised flooding cutting off mine access for 24 days in H1 labour shortages congestion arising from limited dumping locations while keeping manned and unmanned AHS fleets separate A solid H2 with improved mine sequencing AHS development will continue for a further 12 months in FY24; weather and labour improvements delivering gains Managed ROM coal production (Mt) Guidance range 10.1 11.2Mt 9.6 5.6 12.7 H2 11.7 11.2 11.0 10.7 9.7 7.8 3.9 H1 91 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24e