Status of ongoing expansion projects
Dwarka - 300 beds
MAX
Application of OC has been submitted in October.
Lift installation and other finishing work are in
progress.
All key functional heads are in place, middle level staff
being recruited.
Expected commissioning by end of Q4 FY24, subject to
developer obtaining the OC.
Sec. 56, GGN - 300 beds in Phase I
•
Mohali - 190 beds
MAX
3
Nanavati - 329 beds in Phase I
MAX
All statutory approvals to start the construction have
been received.
Design development is under finalization and base raft
concrete activities have started.
Basement and ground level structures have been
completed.
Steel fabrication above ground floor has begun.
Project is largely on schedule.
.
Project is largely on schedule.
Saket Complex (Max Smart) – 350 beds in Phase I
-
Saket Complex (Vikrant) - 300 beds in Phase I
Max Smart Phase I
Vikrant
Saket (East & West)
MAX
Approval for structural drawings has been received in
Jan 2024.
Design development is ongoing and RCC works have
commenced.
Project is largely on schedule.
•
Tree transplantation work is underway, with 159 trees
transplanted and balance 316 trees in process.
Existing structures have been demolished as per plan
and shoring work for sewage & water treatment plants
is ongoing.
Barring the initial delay of 6-7 months the project is on
schedule.
•
Building plans have been re-submitted to Municipal
Corporation of Delhi (MCD) post their initial review.
Dues for water & sewer infra charges have been paid,
while Forest NOC has also been applied.
Tender documents are under review for floating to the
contractors.
Project is largely on schedule.