Record of Adhering to Project Schedules
Estimated Project Development Schedule
Schedule
Nam Tai Inno Park
Nam Tai Technology
Center
Nam Tai Longxi
Land Use Permit
June 2015
May 2018
June 2020
Land Use Rights Certificate
September 2015
March 2019
May 2020
Construction Land Planning Permit
August 2017
May 2019
December 2020
Main Structure Construction
Permit
May 2018
July 2019
December 2020
Main Structure Completion
December 2019
Acceptance Certificate
Property Ownership Certificate
Delivery
Obtained
June 2020
Launched from Q3
2020 to June 2021
Remarks: Detailed development schedule for Nam Tai Inno Valley is not yet available as the project is still pending approval for urban
renewal.