Green Hydrogen Work Progress Update
Peachtree Georgia
2023 Schedule Milestone Summary
✓ Fill/Flush on ELX skids - June 2023
✓ ELX Stack Installs - July 2023
✓ Systems available for pre-commissioning - July 2023
✓ SMA Rectifier Commissioning Start - July/August 2023
H2 Production - August 2023
Construction Details
✓ Completed - Equipment Installations
✓ Completed - Cold & Hot Commissioning on Rectifiers
✓ Completed - Commissioning ELX Equipment
➤ In Progress - Commissioning Liquefaction Equipment
➤ In Progress - Plant Automation & Programming
•
Plug Major Contractors & Vendors
S&B EPC Contractor
-
Completed over 800,000 Safe Work Hours with Zero
Recordable Safety Incidents
Installation He Compressor
Testing Final ELX Skid 2 Loops
•
SMA
•
•
-
Rectifiers
Chart Liquefaction & Storage
-
Priority Power - Plant Mini-Substations
• ABB - Power Distribution Centers