NHPC: Projects Under Construction Project Under Construction-Standalone NHPC Project Installed Capacity (MW) Design Energy (MU) Type of the project CCEA Estimated Cost (Rs. Crore) (Price Level) Anticipated Project Cost (Rs. Crore) 28 एनएचपीसी NHPC Provisional Project Expenditure till -March'23 (Rs. Crore) Expected Commissioning Schedule Subansiri Lower (8X250) 2000 7422 Assam/ Ar. Pradesh Run of River with small pondage 6285.33 (Dec'02) 21247.54 (completion. level)) 17985.13 FY 24-25 (Q-3) Parbati II (4X200) 800 3124 Himachal Pradesh Run of River with small pondage 3919.59 (Dec'01) 11134.54 (July'22) 10512.65 FY 23-24 (Q-4) Dibang (12X240) 2880 11223 Arunachal Pradesh Hydropower cum flood moderation 31876.39 (May'21) 31876.39 (May'21) 2146.96 FY 31-32 (Q-4) scheme Total (A) 5680 21769 42081.31 64258.47 30644.74