Meyer Burger Investor Presentation
Unique opportunity to accelerate growth based on a utility
offtake agreement and strong residential business
Expected available nameplate capacity, volume produced [GW]
3.01
Nameplate EOY
Produced (Expected)
1.0
0.32-0.37
1.4
1.0-1.2
Approximately 3 GW nameplate by EOY 2024 with 1/3
utility and 2/3 residential split
.
•
•
1.4 GW cumulative capacity at the Thalheim (cell) and
Freiberg (module) sites currently being prepared, with
400 MW operational and remainder planned to come online
stepwise in 2022 and 2023
Immediate continuation of expansion to approximately 3 GW
planned at Thalheim and Goodyear (AZ) sites (1 GW utility,
0.5 GW rooftop), expected to come online in 2024, subject
to financing
Contemplating potential capital increase of approximately
CHF 250 million to be launched in the next months for
purposes, inter alia, of financing the planned accelerated
capacity expansion
2022E
1) Approximate capacity
MEYER BURGER
2023E
2024E
Meyer Burger Technology AG, Presentation for Investors, Analysts and Media, August 18, 2022
17View entire presentation