Achieving 400 Mtpy capacity level ... and also in Itabira Main projects and initiatives Tailings filtration plants construction Cauê plant (77% of physical progress) and Conceição plant (75% of physical progress) Start-up by end of 2021 Tailings piles areas Licensing and preparation of areas to receive dry tailings from filtration plants Itabiruçu dam raising Construction starting in 2022 (dry season) and completion by beginning 2023 www. TOSERPRETAT ESASIN Py L Cauê plant construction works Conceição plant construction works VALE 30