Investor Presentaiton
One of Indonesia's largest IPPs
Adaro Power's gross power generation capacity stands at 2,260 MW
adaro
Size / Tech.
Shareholders
COD
Makmur Sejahtera Wisesa - CFPP
Availability Factor
2 x 30 MW CFB technology
100% Adaro Power
#1 Jun 2013, #2 Feb 2014
80% (Avg. 1H23)
Adaro Mining
Electrification
Current: 11.7 MW
Plan: additional 17.9 MW
Makmur Sejahtera Wisesa - Solar PV
Size
130 kWp + 467 kWp
Shareholder
100% Adaro Power
COD
Q3 2018 (for 130 kWp) & 467 kWp COD
27 December 2021
Project cost
USD 800,000 (approx.)
Electricity
produced
395.26 MWh (1H23)
Bhimasena Power Indonesia - CFPP
Size / Tech.
Shareholders
Project cost
Availability Factor
2 x 1,000 MW Ultra Super Critical
34% AP, 34% JPower, 32% Itochu
USD 4.2 billion
87.22% (Avg. 1H23)
Tanjung Power Indonesia - CFPP
2 x 100 MW CFB technology
65% AP, 35% Korea EWP
USD 545 million
Size / Tech.
Shareholders
Project cost
COD
2019
Availability Factor
94.3% (Avg. 1H23)
Apart from improving the performance of its already-operated
power plants and completing the construction, Adaro Power
continues to study renewable power projects such as
biomass, wind power, and solar PV to support PLN through
unsolicited proposal and tenders. Adaro Power is also in the
process of developing captive use power generation projects
for the Group's other business units such as IBT (Genset &
Solar PV) and ADMR (Mini-hydro)