Area 1 growth opportunities Internal Mogbwemo Feasibility Study conducted Sierra Rutile has investigated the development of the Mogbwemo Tailings Project to reclaim waste tailings. A Project involves draining the Mogbwemo pond and mining 12.7Mt of tailings at 1.32% rutile. Work to date included spiral test work (3rd party and on-site plant scale), drilling and geological modelling, a tender for the design and supply of the plant, preliminary process engineering and flowsheet development and lowering of the Mogbwemo pond level. Mogbwemo offers the potential to reduce operating costs and increase mine life at Area 1. Capex of $20m to generate >40% incremental IRR. Timing of investment contingent on improved market conditions and satisfactory resolution regarding Third Amendment Agreement. Sierra Rutile 2023 Half Year Results Presentation | ASX: SRX Sierra Rutile Koppa Dam Embankment 7