The Africa Challenge – Khemisset Potash Project

- KHEMISSET PROJECT – KEY METRICS Mine life Extraction rate Average Annual MOP production Average Salt Production AISC FOB Casablanca ($/tonne) Upfront CAPEX MOP price per tonne Payback Average annual EBITDA LOM EBITDA Margin Post Tax Cash Flow After-tax NPV 8% After-tax IRR 2020 Feasibility Study 19 years 6.0 million tonnes 735k tonnes 1.0 million tonnes US$158/t US$411m US$412/t 2.4 years US$294m 61% US$4.4bn US$1.4bn 40.6% 8