Progressing on regulatory matters Missouri rate case - procedural schedule issued May 18 Third-party testimony due AUG AUG. 31 (revenue requirement) SEPT. 9 (cost of service) SEPT OCT Public Hearings OCT. 12-18 FEB. 28 Latest date rates effective NOV DEC JAN FEB MOPSC Hearings NOV. 28-DEC. 9 Missouri ISRS . $8.5M in annual revenue approved effective May 7 • Request filed June 3 for $11.9M STL Pipeline • MoPSC staff issued report May 27, concluding decision to build STL Pipeline was reasonable and prudent • Received positive EIS from FERC staff June 16 Storage FERC 7(c) received May 19, approving Clear Creek expansion (to 20 Bcf from 4 Bcf) ● Notice to Proceed issued June 21 . We continue to evaluate our development plans 4 Spire | Investor presentation - August 2022 S