Investor Presentaiton
NHPC - Projects in Operation... contd.
Renewable Energy
एनएचपीसी
NHPC
24
S.No
Project
(MW)
Installed Design
Capacity Energy
(MU)
Capital Cost
Year of
Comm.
as on
31.03.2020
Tariff 19-20
(Rs./unit)
Place of Project
Wind Power
50
94.25
2016
330.40
3.67
Lakhmana, Jaisalmer
2
Solar Power
50
105.96
2018
290.59
4.41
Theni/Dindigul District, Tamilnadu
Total-B
100
200.21
620.99
Sub Total Stand-alone(A+B)
5551
24874.35
40217.18
3.36
Operational Projects with Subsidiary
Installed
Design
S.No
Project
Capacity
Energy
Year of
Comm.
Capital Cost
Tariff 18-19
(Rs./kwh)*
Type of the project
(MW)
(MU)
1
Indrasagar, (8x125)
1000
1442.70
2005
4865.09
3.71
Storage
Madhya Pradesh
2
Omkareshwar,
520
677.47
2007
3152.66
5.96
Storage
(8x65)
Madhya Pradesh
Total-C
1520
2120.17
8017.75
* Tariff for 2019-20 yet to be
notified.
Grand Total-
7071
26994.52
D:(A+B+C)View entire presentation