2020 Operating Expenses
Change in the commercial cycle in 2019
⚫ Shift by 3 to 15 months of the equipment delivery to the customer
⚫ The order taking and installation activities remained unchanged
⚫ The cash stream remained unchanged: deposit at order and final payment at acceptance
⚫ Decreased working capital thanks to reduced time from equipment production to installation
One-time transition impact on equipment revenue, as equipment billing (at delivery) are delayed until customer site readiness
Up to December 2018
Sales
Agreement
Since January 2019
Sales
Agreement
Cash cycle unchanged
EOS
Downpayment
Equipment
Delivery
Site Preparation by the Customer
[3 to 15 months]
Installation
& Acceptance
Site Preparation by the Customer
[3 to 15 months]
Equipement
Delivery
CONNECTING IMAGING TO CARE
Installation
& Acceptance
Final Payment
imaging