A World-Class Investment in Food Security
Autazes Project Detail: Milestone Schedule
Key Permits to Start of Operation
Preliminary License (LP)
Installation License (LI)
Current Status
Operational License (LO)²
Obtained
Location, social and environmental
approval of the project
■ Awarded by IPAAM1
·
Requirements to be fulfilled in the project
Permits Completed To Date
✓ Preliminary License (IPAAM / AM) - completed
Installation License (IPAAM / AM) - mid 2022
Archaeological Studies Authorization (IPHAN) -
completed
Archaeological Site Delimitation Authorization
(IPHAN) - completed
In Progress
Provides authorization to initiate construction
Obtain by: (i) fulfillment of LP conditions; (ii) approval
of the mine development plan (PAE); (iii) and approval
of the Basic Environmental Plan (PBA)
76 of required 78 items approved and 77th item being
Indigenous Consultation Study submitted Q4 2022
Archaeological Site Rescue Authorization (IPHAN) -
completed
Final Geological Survey Report (ANM) - completed
Mining Decree (ANM) - upon receipt of Installation
License
Future
Grant of Mining Concession by Mining and
Energy Ministry
■ Requires inspection of constructed mine
and plant to ensure compliance with codes
Purchase of building land - key purchases
completed
Port Authorization (Navy) - upon receipt of
Installation License
Port Membership Agreement (ANTAQ) - upon
receipt of Installation License
Source: Brazil Potash; Notes: (1) Environmental Protection Agency of the State of Amazonas; (2) Valid in increments of four to ten years and can be renewed as necessary until end of mine life