Recovery of power costs Annual power cost update tariff • Annual reset of prices based on forecast of net variable power costs (NVPC) for the coming year • Subject to OPUC prudency review and approval, new prices go into effect on or around January 1 of the following year Power Cost Adjustment Mechanism (PCAM) Power Cost Sharing Customer Surcharge 90/10 Sharing 8.5% Earnings Test for 2018 Customer Surcharge $30 million Baseline NVPC ($15) million 90/10 Sharing Customer Refund Deadband Return on Equity 9.5% 10.5% Customer Refund • PGE absorbs 100% of the costs/benefits within the deadband, and amounts outside the deadband are shared 90% with customers and 10% with PGE • An annual earnings test is applied, using the regulated ROE as a threshold • Customer surcharge occurs to the extent it results in PGE's actual regulated ROE being no greater than 8.5%; customer refund occurs to the extent it results in PGE's actual regulated ROE being no less than 10.5% Portland General Electric 27