Eldorado Gold Operational and Financial Update
2023 Focus
Project cost and schedule are on track for mid-2025 commissioning
Sept 30, 2023
34%
Project Process
56%
Detailed engineering
000
Procurement
Expected progress by end
of 2023
48%
-90%
73%
-90%
Capital Expenditure
$101 M
Employees/contractors
onsite
eldorado gold
$160 -
$170 M
00000
☐
ப
L
400
О
☐
900
2023 Site Activities
Mobilization of construction contracts for
earthworks, concrete, process plant piping and
electrical works
Awards of the remaining major procurement
and contract packages
Complete 400m of UG development and
associated services
Mobilization of embankment construction for the
IEWMF
Mobilization of mechanical, piping and electrical
installations in the mill
General works continued to be focused on site
preparation, relocation of temporary facilities,
and the haulage of aggregates to site for
construction purposes
Power service installation advanced with the
installation of the new substations and
distribution to the underground network. Power
service upgrades are scheduled for completion
in Q4 2023
12
☐
Advance the water management systemsView entire presentation