Green Energy, On Demand slide image

Green Energy, On Demand

Up to 200MW Kidston Wind Project Development Targeting bringing the Project to financial close in 2H CY2023 and commencement of operations in 2H CY2025 Development funding agreement signed with J-POWER to earn 50% in the project through initial investment Combination of wind, solar and hydro completes the Kidston Clean Energy Hub (a globally unique integration) Will leverage existing infrastructure (transmission line) and co-location advantages to K2-Hydro WORKSTREAM Land agreements and development approvals Resource monitoring and yield assessment Supplier(s) and contractor(s) tendering and contracting Grid connection studies, application and contracting Financing and offtake Financial Close Construction Commissioning/Operations Genex | Green Energy, On Demand | Presentation 1H CY2022 2H CY2022 1H CY2023 2H CY2023 1H CY2024 2H CY2024 1H CY2025 2H CY2025 20 20