Future-Enabling Growth Strategy Update
Woodsmith project update
Prior design
Anglo American
assumption
Ventilation
Mining method
Hybrid model
Scheduled post
possible
expansion
Required earlier
due to mining
method
Marketing
Value in use
estimated
Value in use
opportunities
identified
Continuous
miner
Woodsmith
Greenfield crop nutrients project
Construction continues
•
.
•
•
•
Good progress on conveyor tunnel ~17km complete
Shaft boring commenced in service shaft
FY 2021 capex ~$0.55bn
Technical review largely complete - more detailed engineering
to optimise key elements
Adjusting mine method, shaft schedule & ventilation to our
standards
Upgrading project scope to increase efficiency & scalability for
long term value
Final design engineering, capex & schedule at the end of 2022
POLY4: multinutrient, low chloride fertiliser
Low carbon, organically certified 20
Farm demos confirm crop yields & quality improvements
"Value in Use" work also positive
Anglo American
2