NHPC Renewable Energy and Pump Storage Project Updates
NHPC -Projects Under Survey & Investigation
E S. No.
Projects
Installed
State
Capacity
(MW)
Projects Under FR/DPR Preparation
2 Dulhasti Stage-II UT of Jammu &
(2x130)
Kashmir
260
Total
890
Status
41
एनएचपीसी
NHPC
MOU has been signed between NHPC Ltd. and JKSPDCL on 03.01.2021.
The project shall be executed by NHPC on BOOT basis for the period of 40
years.
1st Consultation Meeting with CEA for preparation of DPR was held on
17.03.2021 and Minutes of Meeting (MOM) was issued on 25.03.2021.
MOEF&CC vide letter dated 16.07.2021 has conveyed the approval to the
TOR for EIA/ EMP studies of the project.
EIA/ EMP studies awarded on 08.09.2021 and are in progress.
No forest clearance is required. NOC has been obtained from Forest
department.
Defence Clearance has been accorded by MoD on 03.01.2022.
As per revised guidelines, all (14 nos.) Pre-DPR chapters have been
submitted to concerned directorates of CEA/CWC/GSI/CSMRS etc. out of
14 Chapters, 10 Chapters cleared.View entire presentation