Central Puerto Financial Overview slide image

Central Puerto Financial Overview

Availability of thermal units²) =2 (2) Steam & Gas turbines (%) 96% 88% 62% 2020 96% 86% 95% 93% 77% 74% 78% 65% 68% 50% 2021 2022 ■Puerto Complex Lujan de Cuyo ■Brigadier Lopez Combined Cycles (%) 89% 91% 93% 75% 2020 35% 2021 2023 Costanera 88% 93% 91% 91% 97%99% 69% 2022 2023 ■Puerto Complex Lujan de Cuyo San Lorenzo Costanera Complex Availability reported by CAMMESA, calculated based on the total installed capacity of each power plant. Central Costanera figures does not consider the power capacity values of the steam generation units COSTTV04 and COSTTV06 for a total installed capacity of 120 MW and 350 MW, respectively S 10
View entire presentation