DIROK PHASE-II DEVELOPMENT Project on-track for delivery of additional gas by Q1 FY21-22 RFDP approved by Managing Committee 1. DRILLING 3 development wells & Appraisal - Appraisal well in North Dirok Increases production from 35 to 55 mmscfd 2. PROCESSING HMGPP capacity expansion Increases capacity from 35 to 55 mmscfd Commercial proposal received from Expro, UK for capacity expansion - Lead time 9 months - Investor presentation Q3 2019-20 3. DELIVERY 35 KM pipeline from HMGPP to marketing hub of Duliajan Will aid in obtaining premium price for additional gas Physical route survey completed Regulatory clearance in process RoU acquisition in progress 00 07 HINDUSTAN OIL EXPLORATION COMPANY LIMITED H❤EC®