$41B in Projected Capital Investment Through 2026: Functional View
Excluding Vogtle 3 & 4
(in $ billions)
2022
2023
2024
2025
2026
Total
'22-'26
New Generation
Generation Maintenance
Environmental Compliance
Ash Pond Closures
Transmission
0.3
0.2
0.0
0.6
0.9
1.1
1.0
0.8
0.9
4.6
0.1
0.1
0.1
0.1
0.1
0.5
0.7
0.7
0.8
0.9
0.9
3.9
1.5
1.6
1.6
1.7
1.6
8.1
Distribution
1.7
1.7
1.7
1.8
1.8
8.8
Nuclear Fuel
0.2
0.3
0.3
0.3
0.4
1.4
General
0.6
0.6
0.8
0.7
0.6
3.4
State-Regulated Electrics (excl Vogtle 3&4)
6.0
6.4
6.3
6.3
6.2
31.1
State-Regulated Gas LDCs
1.6
1.7
1.7
1.6
1.7
8.3
Total State-Regulated Utilities
7.6
8.1
8.0
7.9
7.8
39.4
Southern Power
GAS Pipelines & Other
0.1
0.2
0.1
0.1
0.1
0.6
0.1
0.1
0.0
0.0
0.0
0.2
PowerSecure
Other
Total Consolidated
8.1
8.4
8.2
8.1
8.0
40.9
Total Consolidated (excluding Ash Pond Closures)
7.4
7.7
7.5
7.2
0.1
0.0
0.0
0.0
0.0
0.1
0.2
0.1
0.1
0.0
0.0
0.5
4
7.1
36.9
27