Freyr Results Presentation Deck
Giga America update
Phase 1a status
Presentations to select strategic and prospective financial sponsors
ongoing
Seeking to raise $1 billion of project-level equity
Permitting for pre-construction, construction, and ongoing
operations approvals are underway
There are no concerns that permits will impede progress or
become critical path
Accelerated schedule to support Gen2, design protecting for future
upgrade to next-generation process design
Detailed equipment engineering and planning for procurement
of long lead equipment has begun
Front-End Engineering Design initiated with Building & Infrastructure
engineering and architecture team
Electric utilities contract negotiations are nearing completion
Applications in process under U.S. DoE funding programs
Targeting FID and start of construction in 4Q 2023
FREYR
9View entire presentation