Endeavour Mining Investor Presentation Deck
BOUNGOU MINE
Burkina Faso
Overview
MINING
Quick Facts
Timeline
ENDEAVOUR
130-140koz
2022 Target
Production
2017
Endeavour successfully integrated the
Boungou mine within its West African
operating platform in Q3-2020.
The Boungou mine is a low cost, high grade
operation with significant exploration
potential. The mine was built on time and on
budget and achieved commercial production in
Q3-2018.
Ownership
90% EDV
10% Burkina Faso
AK
2018
Construction began in
March 2017
COO video presentation
$900-1,000/oz
2022 Target
AISC
Mining Type
Open pit /
Contractor Mining
O
Website
First gold pour in June and
commercial production achieved
in September
2019
Mining activities recommenced in Q4-2020 following
the appointment of a local West African mining
contractor.
As the area around the mine is virtually unexplored
and significant opportunity exists to identify
additional resources, Endeavour commenced
exploration activities in late 2020.
Processing Rate
1.5Mtpa Gravity /
CIP plant
Ö
2020
Latest technical report
1.1 Moz
As at
December 31, 2021
P&P Reserves
Placed on care and maintenance
in November
Royalty
3%-5%
sliding scale
Restarted processing stockpiles in
February
2020
3D mine site tour
1.4 Moz
As at
December 31, 2021
M&I Resources
AL
BURKINA FASO
Wahgnion Mine
Mana Mine
Houndé Mine
Ouagadougou
>
Boungou
Mine
Corporate Tax
27.5%
Mining operation successfully
restarted in October
93View entire presentation