NTPC Sustainability and Growth Presentation slide image

NTPC Sustainability and Growth Presentation

Huge Capacity Addition Lined up Ensuring Availability Land Water 73,024 Fuel EC/FC PPAs Current Capacity pipeline (in MW) 17,463 Installed Capacity Under Construction 39,513 एनटीपीसी NTPC Investment Approval 1,30,000 + Under feasibility & balance Total by 2032 Snapshot of Projects Under Construction Fuel Mix In MW Coal Technology In MW Group Mix In MW Coal 9,300 Ultra Super Critical 6,640 NTPC 6,569 Hydro 2,255 Super Critical 2,640 Domestic JVs 10,234 RE 5,908 Sub Critical 20 International JV 660 Total 17,463 Total 9,300 Total 17,463 D:: 20