Q3 FY 21-22: Salient Orders Secured Service Туре Project scope Domestic Project Management Consultant for Two LNG Consultancy Storage tanks at Dahej LNG terminal Overseas Consultancy (Gujarat) FEED Engineering related to Debottlenecking the existing produced Water Treatment Plant Capacity from 200 MBD TO 300 MBD For 1 MMBD Phase-1 Project (EIL Client Contract Value (Rs. Million) Award Date Completion Date Petronet LNG Ltd (PLL) 275 Oct 2021 June 2025 ADNOC Offshore 67 Oct 2021 Mar 2022 Various engineering services assignments Consultancy under empanelment agreement with Client (4 nos) ADNOC Offshore 62 Nov 2021 Oct 2023 Delivering Excellence through People 17