2013 Processing & Mining Performance slide image

2013 Processing & Mining Performance

2013 Mining Performance (1/2) Total bcm mined in 2013 [ths. bcm] 900 845 5 648 6 000 800 754 687 5 000 700 623 600 558 561582 547 4 000 491 500 3 000 400 300 2 000 200 1 000 100 0 0 Jan Feb Mar Apr May Jun Jul Aug Sep 2013 actual Ths. BCM Comments: . Mining tonnage: total tonnage forecast for 2013 is 14125kt to be mined from 3 pits 3/5, 2N2K and GT • Shifts; 2 X 12 hrs shift are worked at Taparko with hot seat change and 45 minutes lunch break • Mobile mining fleet maintenance is conducted during lunch break • Strategy for 2014 is to develop Bouroum, GT and 3/5 on best NPV analysis basis nordgold 21