Key Project Updates - BPSL & Other Downstream Phase-II Expansion from 3.5 to 5 MTPA Key equipment received at site for Wire Rod Mill-2, SMS-2, Lime Calcination Plant-6. Civil, Structural & Equipment erection work in progress Project expected to be completed by the end of FY24 Other Downstream Projects • 0.12 MTPA Colour Coating line in Jammu & Kashmir o Civil work at site and equipment erection in progress o To be completed by FY24 JSW Steel Corporate Presentation: August 2023 JSW Steel Ladle Turret & Casting Platform at SMS-2, BPSL Phase-II 45 45