NHPC Capacity Addition and Financial Overview
Renewable Energy
A (i) Standalone (Ownership Based)
(a) Under Construction
S.No
Name of Project
19
एनएचपीसी
Estimated
Capacity
(MW)
Expected
Capital cost Commissioning
(in Crs.)
Tariff
(Rs./unit)
Status of PPA
Schedule
NHPC
1
Solar Power Project, Ganjam (Odisha)
40
178.00
2023-24
2.75 PPA Signed with GRIDCO
2
600 MW Grid Connected Solar Power
Project under CPSU Scheme, Gujarat
600
4295.63
2024-25
2.45 Consent for procurement
of power received for 1000
MW.
3
300 MW Grid Connected Solar Power
Project under CPSU Scheme, Rajasthan
300
1731.57
2024-25
4
100 MW Grid Connected Solar Power
Project under CPSU Scheme, Andhra
Pradesh
Total-(a)
100
577.20
2024-25
1040
6782.40
Power Usage Agreement
2.45 with WB DISCOMS for 100
MW signed on 23.11.2022.
Power Usage Agreement
with DISCOMS (Telangana)
for 500 MW signed on
2.45 28.03.2023.View entire presentation