B 1Grou Selected projects update Emerald Hills The heating plant for the Emerald Hills project is fully automated and built using the latest technologies available. Today the heating plant is 90% complete and is on schedule to begin functioning on time for the completion of Stage 1 of the building project. The heating plant has six boilers with a total capacity of 78 MWt. Hot water is supplied to the residents of the Emerald Hills complex by heat exchangers located directly in each of the buildings. EMERALD HILLS 32 32