Property Marketing and Sales Review

As of Jun 21, construction for all of 2019's legacy projects have been completed Cost to Completion $230 $212m Construction Progress (1) Percent Complete 100% 90% SOLIPPO PT LIPPO KARAWACI TOK 100.0% 97.9%99.0% 88.9% 81.9% $180m $160m $110m $87m $54m 80% 71.7% 70% 60% 50% 40% 31.7% 30% 42.4% 54.2% 20% $36 $21 10% $0 0% 1019 2019 3Q19 4Q19 1Q20 2020 3020 4Q20 1Q21 2Q21 2019 3019 4Q19 1020 2020 3Q20 4Q20 1Q21 2Q21 (1) Cost to complete does not include late delivery penalties and other costs outside of construction costs 12