NHPC: Projects Under Construction Project Under Construction-JV S.No Projects Installed Capacity (MW) Design Energy (MUs) Cost (In Cr.) & PL Expected Commissioning Schedule Status एनएचपीसी 26 NHPC 1 Chenab valley Power Projects Ltd. (JV between NHPC (49%) JKSPDC (49%), & PTC (2%) i) Pakal Dul (4x250) J&K 1000 3330.18 8112 (Mar 13) FY 25-26 (Q-2) ii) Kiru (4x156) J&K 624 2272.02 4288 (July18) FY 24-25 (Q-2) ■ Civil construction activities for Power House and Dam works are in progress. ■ Letter of award for HRT-TBM Package issued on 03.07.2020. LOA's for all the three packages have been issued on 24.02.2020. ■ Contractors have started mobilisation after signing of agreement. TOTAL (C) 1624 5602.20 12400 Grand Total (A+B+C) 4924 18531.86