Investor Presentaiton
NHPC: Projects Under Construction
Project Under Construction-JV
S.No
Projects
Installed
Capacity (MW)
Design Energy
(MUs)
Cost (In Cr.) & PL
Expected
Commissioning
Schedule
Status
एनएचपीसी
26
NHPC
1
Chenab valley Power Projects Ltd. (JV between NHPC (49%) JKSPDC (49%), & PTC (2%)
i)
Pakal Dul (4x250)
J&K
1000
3330.18
8112
(Mar 13)
FY 25-26 (Q-2)
ii)
Kiru (4x156)
J&K
624
2272.02
4288
(July18)
FY 24-25 (Q-2)
■ Civil construction activities for Power House and Dam
works are in progress.
■ Letter of award for HRT-TBM Package issued on 03.07.2020.
LOA's for all the three packages have been issued on
24.02.2020.
■ Contractors have started mobilisation after signing of
agreement.
TOTAL (C)
1624
5602.20
12400
Grand Total (A+B+C)
4924
18531.86View entire presentation