Strong Bidding Pipeline
SKIPPER PEFRORMACE HIGHLIGHTS
Limited
Performance Update
Revenue and Profitability was impacted on account of -
☐ The spread of COVID 19 impacted the business from mid-March, which culminated into scaling down
of operations post the national lockdown, by way of interruption in production, supply chain
disruption, unavailability of personnel, closure / lockdown of production facilities etc.
☐ All of the Company's Plant remained under shutdown for the entire month of April'20.
☐ Starting May'20, the company have partially resumed Manufacturing & Dispatch operations across
its plant, but the operational activities continued to remain compromised with government
mandated social distancing measures in place.
Super Cyclonic Storm "Amphan" a powerful and deadly tropical cyclone that caused widespread
damage in the state of West Bengal and Kolkata region also severely disrupted plant operations and
adversely impacted business performance for almost 10 days in May'20.
☐ Good recovery from June onwards, revenue of June'20 better than corresponding months of last
year.
☐ All of the manufacturing units are now operating at pre-COVID level of production.
7View entire presentation