PROJECT HIGHLIGHTS CONTINUED
Completed ~$3.0 million program Q4 2020 primarily directed
at metallurgical and geotechnical drilling, and on-going
environmental studies to advance feasibility and permitting
Approved an $18 million 2021 program to conduct resource
in-fill and condemnation drilling, hydrology, geotechnical
metallurgy studies along with engineering and environmental
studies to support completion of a feasibility and permitting.
Initial environmental permitting activities are expected to
commence the H2 2021.
Au
@ghorof
- 2
>10
>-30
•
Current Plan is to complete Feasibility Study by the end of
2022 and Permitting by 2023.
Project construction is expected to take approximately one
•
•
•
year, with production planned to commence in 2024.
Initiated community outreach meetings with communities
around the project area and along the Alaska Highway route.
Continue to hold productive meetings with Tetlin Tribe
Leadership, who have indicated their support for the project
development plan.
50mm
100 m
Plan View
OPEN
Current Topography
Illustrative Pit Shells
(@ $1,200/oz Au)
OPEN
A'
16