Investor Presentaiton
Mayskoye
850ktpa underground mine and flotation concentrator on site for a capital
cost of c. US$ 150-170 million.
Q1 2010 highlights
Underground development in progress
• First stopes expected to be ready for production in 1H 2011
• Construction of water reservoir and tailings impoundment in progress
Foundation works for the flotation concentrator to commence in Q2 2010
⚫ Steel required for the construction of the structural steel frame planned
•
.
•
To be delivered during the summer 2010 navigation
To be installed in the winter of 2010/2011
Results of the FS and reserve statement to be released in Q3 2010
Resources
Ore tonnes (Mt) Au grade (g/t) Au (Moz)
MI&I
© 2010 Polymetal
19.8
11.8
Pevek
Maiskoe
Nikolaevsk-on-Amur
Amurs k
POX
Bering Sea
-4800 km
by sea
Sea route
7.5
© Deposit
Settlement:
21