Strategic Priorities and Growth Outlook

Sarda Energy Project Expansion Plan Steel (Pellet plant) Capacity pre- Post-expansion Incremental Spend till date expansion Capacity Capex 6.0 Lakh MT 7.5 Lakh MT Nil Nil 2 Lakh MT 3 Lakh MT Rs 25 Crores Rs 10 Crores (Billet plant) Steel Ferro Alloys 111 MVA 144 MVA 125 Crores Rs 1 Crore Hydro Power 29 MW 149 MW 1430 Crores Rs 835 Crores Remarks SARDA SARDA ENERGY & MINERALS LTD. Approvals are required and Pellets will also be sold externally along with captive consumption The upcoming Steel plant will be commissioned by FY19 which will lead to higher capacity utilisation Capacity utilisation by commissioning of Vizag plant will be increased by FY 2020 Sikkim Hydro Power plant (96 MW) will be commissioned by FY 2020 and Chhattisgarh power plant (24 MW) will be commissioned by FY 2022 22 22