2022 State Budget: Fiscal Policy and Structural Reform
National Strategic Project (PSN) Completed in Q1-2021
33
(16%)
PSN Progress Status 201 Projects + 10 Programs
(January-June 2021)
18
(8%)
44
(21%)
6 PSN Projects Completed in Q 1 - 2021
Completed (IDR 136,6T)
1
Partially Operated (IDR 2.294,3T)
8
Construction (IDR 1.990,3T)
Medan -
Binjai Toll
Road
2
Cengkareng -
Batu Ceper -
3
Kuningan
Dam
Kunciran
Toll Road
(4%)
Transaction (IDR 365,6T)
Preparation (IDR 875,5T)
4
Passeloreng
Dam
5
Semarang Barat
Water Supply
System
6
Umbulan
Water Supply
System
108
(51%)
PSN Investment Contributor
Total IDR 5.607 Trillion*
State
Budget
11%
Private
67%
SOES/
RSOES
22%
* Exclude Regional Development
Acceleration Program (Perpres 79 an 80/
2019) and Bali Utara Airports
Source: Committee for Acceleration of Priority Infrastructure Delivery (KPPIP)
6 PSN Projects Completed in 1st
Quarter in year 2021 with estimated
investment value IDR 13,5 Trillion and
25 PSN Projects are partially operated
with estimated investment value IDR
394,6 Trillion
197View entire presentation