Biannual Shut Strategy being formulated Vision "To develop, implement and sustain an optimal comprehensive shutdown strategy that maximises plant uptime and provides operational stability at the lowest cost without negatively impacting on workplace safety or asset integrity." Current Shutdown Delivery Approximately 34 weeks in a year have a major shutdown event within the Lihir Process Plant, this includes Mills, Crushers, Autoclaves etc. Opportunity - FY21 Aug/Feb Improved alignment of maintenance shutdowns in the grinding and autoclave areas has potential to improve both plant uptime and recovery. A lower frequency of major shutdowns has benefits both in terms of operational stability and improved maintenance work management. Notes: Shutdown plan at concept level of development 20 20