Investor Presentaiton
Biannual Shut Strategy being formulated
Vision
"To develop, implement and sustain an optimal comprehensive shutdown strategy that maximises
plant uptime and provides operational stability at the lowest cost without negatively impacting on
workplace safety or asset integrity."
Current Shutdown Delivery
Approximately 34 weeks in a year have a major shutdown event within the Lihir Process
Plant, this includes Mills, Crushers, Autoclaves etc.
Opportunity - FY21 Aug/Feb
Improved alignment of maintenance shutdowns in the grinding and autoclave areas has potential
to improve both plant uptime and recovery.
A lower frequency of major shutdowns has benefits both in terms of operational stability and
improved maintenance work management.
Notes: Shutdown plan at concept level of development
20