These projects are located all over the country including AJ&K. Location wise detail is given in the chart
below:
CPEC Energy Chapter - PPIB
11,648 MW
Commissioned Projects
(4,620 MW-40%)
Under Implementation
(7,028 MW - 60%)
Punjab (18%)
2,040 MW
CPEC POWER PROJECTS - LOCATION WISE
AJ&K (16%)
1,824 MW
Balochistan (14%)
1,620 MW
KP (7%)
884 MW
Sindh (45%)
5,280 MW
Total = 11,648 MW
*720 MW Karot HPP located at dual boundary of Punjab and AJ&K
Kohala
10%
Hub Power
11%
Azad Pattan
6%
Suki Kinari
Karot
6%
8%
Gwadar.
4%
Thar Energy
5%
Sahiwal
11%
Engro
14%
ThalNova
5%
Hub Power
28%
Kohala
16%
Port Qasim
11%
Port Qasim
29%
Azad Pattan
10%
Shanghai
19%
Suki Kinari
12%
Sahiwal
Karot
10%
Oracle
19%
Oracle
11%
Engro
6%
Shanghai
11%
Gwadar
3%
ThalNova
3%
Thar Energy
3%
Brief status of projects under CPEC as on 30th June 2020 is defined in the below image
CPEC Power Projects - PPIB Portfolio
Hydropower Projects
Pre-LOS Stage
LOS Stage
4 Projects
3,428 MW
2 Projects
1,824 MW
Construction
Stage after EC
Commissioned
2. Projects
1,604 MW
Total investment outlay of energy and transmission line projects being processed by PPIB under CPEC
is around US$ 21 billion which is a huge investment considering the fact that this has been made in a
single sector of Pakistan's economy. The FY-20 was another productive year for CPEC based power
generation and transmission line projects, as despite the outbreak of COVID-19 Pandemic, majority of
the projects picked momentum in accomplishing various milestones. However, some marginal
variations in timelines of advance stage projects are anticipated due to which COD schedule of few
projects may be delayed marginally.
Due to fast-track processing by PPIB, the portfolio of 13 power generation and one transmission line
projects under CPEC has acheived significant progress within a period of 3-4 years. Accordingly, Coal
based energy chapter of CPEC is expected to be concluded by end 2023 while hydropower projects
being different in nature and involving more complicated and time consuming activities as compare
to traditional thermal power generation projects would go beyond 2023. With all out efforts of PPIB and
support of all stakeholders including the Power Division, federal & provincial entities, NEPRA and CPEC
Secretariat, four (4) coal based power projects (3 x imported coal based projects of 3,960 MW and 1x
These coal based project of 660MW) totalling 4,620 MW have already been commissioned. In addition
to these commissioned IPPs, another nine IPPs are under processing out of which 8 IPPs are at
advance stages of development.
Thar Coal based Projects
Pre-LOS Stage
LOS Stage
5 Projects
3,960 MW
1 Project
2 Projects
1,320 MW
1,650 MW
Imported Coal based Projects
Pre-LOS Stage
4 Projects
4,260 MW
LOS Stage
I Project
300 MW
Transmission Line Projects
Pre-LOS Stage
LOS Stage
1 Project
4,000 MW Transmission Capacity
Commissioned
Construction
Stage after EC
1 Project
330 MW
1 Project
600 MW
Construction
Stage after EC
Commissioned
3 Projects
3960 MW
Construction
Stage after EC
1 Project
4,000 MW
Transmission capacity
Commissioned
CPEC has a commendable contribution in overcoming electricity shortages in Pakistan as well as
diversifying the country's fuel-mix. Completion of all CPEC projects will provide Pakistan a number of
new corridors of success and economic prosperity in the years to come. The scale of development is
increasing under CPEC and it is well on track to provide new avenues of success for Pakistan in the
years to come. However, slight variations in the completion schedules of few projects cannot be ruled
out in the backdrop of Covid-19 outbreak.