Growth Strategy - Processing Plant
Upgrade and expansion of the Processing Plant to enable higher processing throughput to become a centralized plant to process ores
from both the Eastern Corridor and the Western Corridor.
2021 - 2022
2022 - 2025
Upgrade and expand the Processing Plant capacity to
5.6Mtpa by end 2022.
By end of 2025(1), the Processing Plant will be able to process up to 8.0 Mtpa of
throughput to cater both the Eastern Corridor and the Western Corridor.
4.0
Q2 2021
5.6
2022E
Note:
(1) Processing Plant capacity of 8.0 mtpa is expected by end of 2025, full impact will be reflected in 2026 operation.
~450 koz of Gold
Production Capacity
(with the assumption of average Gold
Head Grade maintained at least 2.0 g/t)
8.0
2026E