We maintain in Santo Antônio dos Lopes, Maranhão,
the Parnaíba Complex, composed of the thermal
power plants of natural gas generation Parnaíba I,
Parnaíba II, Parnaíba III and Parnaíba IV, in addition
to two projects under development: Parnaíba V and
Parnaíba VI. In total, the contracted capacity is 1.9
GW, of which 1.4 GW is already in operation, and the
generated energy is sent entirety to the SIN, in the
North subsystem, within the ACR.
The complex is one of the largest thermal parks
of natural gas power generation in Brazil and a
pioneer in the use of the integrated Reservoir-to-
Wire model. With gas produced in fields located
around the plants, which allows reduction of costs
and losses in the transportation of fuel, the energy
generated has more competitive prices and lower
environmental impact.
In 2021, we completed the heavy works of Parnaíba
V, with the completion of the Backfeed Qde SE 500
KV, the commissioning of a Water Treatment Plant,
hydrostatic tests completed and in the process of
cleaning and pre-operational tests in boilers and
turbine mounted and in the connection phase of
pipes. Thus, Parnaíba V entered its instrumentation
and control phase, commissioning begins in 2022
and the start of commercialization of its 385 MW of
energy is scheduled for August 2022
Parnaíba Complex and Transmission Line Substation in Santo Antônio dos Lopes, MA
In Parnaíba VI, we signed contracts in 2021 with
the turbine manufacturer and the executor of
the works. Construction will begin in 2022, with
commercial operation scheduled for 2024 and, at
CCR, in 2025. Parnaíba VI will represent the cycle
closure of Parnaíba III, with 92.5 MW added to the
Parnaíba Complex.
Parnaíba II recorded an operational incident in a
turbine and operated, for 30 days, with half its
capacity. After the necessary adjustments, the plant
returned to normal levels of generation capacity.
Parnaíba Complex Assets
PARNAÍBA I
Capacity: 676 MW
Maximum gas consumption: 4.6 MM m3/day
Contract expiration: Dec-2027
Availability: 95%
PARNAÍBA II
Capacity: 519 MW
Maximum gas consumption: 2.3 MM m3/day
Contract expiration: Apr-2036
Availability: 73%
PARNAÍBA III
Capacity: 178 MW
Maximum gas consumption: 1.2 MM m³/day
Contract expiration: Dec-2027
Availability: 97%
PARNAÍBA IV
Capacity: 56 MW
Maximum gas consumption: 0.3 MM m3/day
Contract expiration: Merchant
Availability: 82%
PARNAÍBA V*
Capacity: 385 MW
Contract expiration: Dec-2048
PARNAÍBA VI*
Capacity: 92 MW
Contract expiration: Dec-2049
*Assets in deployment at the end of 2021