Investor Presentaiton
Q1 FY24 Operational Performance
Zero Harm on HSE
■
-
Fatality, 1 LTI
-
Reportable
1 FAC
'
Recordable, 1 MTC-
Zero
Recordable.
Performance
■
◉
Power Transmission: Q1 FY24 Average availability > 99.50%.
Solar Generation (100MW): 61.26 MU are generated at 28.05% CUF
☐
Insulator flashovers led to impact on availability performance.
Reliability
☐
Q1- Trips/Line at 0.24. Substation Trips/Element: 0.10
☐ Technological Initiatives
Invested in RAS (Remote Access Server) & AFAS (Automatic Fault
Analysis System) project, which enables swift analysis of fault data and
enhances decision-making capabilities.
Solarization
☐
Solar Generation - Ground mounted solar plants at Bhopal (205 kWp) and
Dhule (248 kWp) 169,286 units. Additional Solarization projects are
scheduled for implementation in 4 more assets in line with our green
initiatives
☐ Cybersecurity
No severe threats identified via security operation center.
IndiGrid
Q1 FY24 availability(%)
99.68 99.89 99.52 99.57 99.98 100.00 99.93 100.00 99.56 100.00 99.96 99.84
BDTCL
JTCL
RTCL
PKTCL
MTL
PTCL
NRSS-XXIX
OGPTL
ENICL
•
■Availability Over Normative
GPTL
PrKTCL
JKTPL
■Normative Availability
Notes:
All Assets performed above the Normative Availability except NER-II, which faced a
temporary impact on its performance due to insulator flashovers.
No. of Trips / Line
NER-II
100.00 99.36
95.73
RSTCPL
KhTL (Khargone)
Key Indicators
Training Man hours (Hours)
Q1 FY24
0.24
~13,370
Q1 FY23
0.36
~11,734
Loss Time Incident - Recordable (Nos)
Unsafe conditions reporting (Nos)
Near Miss Reporting (Nos)
0
0
1,898
1,975
84
15
Rooftop (SS) Solar Generation (kWh)
Utility Solar (100 MW)
11,904
12,134
Generation (MU)
61.26
57.52
CUF/Plant Availability (%)
28.05%/99.68% 26.34%/99.87%
Consistent track record of maintaining superior availability
*LTI: Loss Time Incident; FAC: First Aid Cases; MTC: First Aid Cases