Investor Relations Presentation
Green Transformation - Comprehensive master plan
Roadmap to reduce CO2 by >30% until 2030 and become a climate neutral steel location by 2045
2019
Trialling H₂ use
in the blast furnace
since 2021
bluemintⓇ Steel
from 2026
First DR plant with melting units (SAF)
Removal of the first coal-based blast furnace
up to 2029
Hydrogen ramp-up
of the first DR plant to 100 %
up to 2030
Removal of the second
coal-based blast furnace
replacement by
DR-based
technology
before 2045
2+45
KLIMANEUTRAL
CLIMATE-NEUTRAL
tk H Steel
Complete implementation of the transformation
Carbon-neutral steel production without coal-based
blast furnaces incl. decarbonization of
the downstream systems
Available quantities of bluemintⓇ Steel per year
2022-2025 50-500 kt/a
75 thyssenkrupp AG | Investor Relations | December 2023
2026 onward ~ 3 mt/a
2030 onward~ 5 mt/a
Avoidance of residual CO2 emissions,
e.g. through Carbon2ChemⓇ (CCU)
2045 onward 11 mt/aView entire presentation